What period do the insurances in the Insurance Table cover?

+1 vote
405 views

What period do the insurances in the Insurance Table cover?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The insurances in the Insurance Table provide cover from the starting date until the Defects Certificate is issued or a termination certificate has been issued (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)