The insurances in the insurance table are in whose name?

+1 vote
345 views

The insurances in the insurance table are in whose name?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The insurances are in the joint names of the Parties. This is also true for those insurances procured by the Employer for those matters at the Contractor’s risk (see Clause 84.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool