Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,496 questions

5,900 answers

1,321 comments

Register its Free

Download here

How is the liability of a Party to indemnify the other reduced if events at the other Party’s risk contributed to the claims, proceedings, compensation and costs?

+1 vote
333 views

 How is the liability of a Party to indemnify the other reduced if events at the other Party’s risk contributed to the claims, proceedings, compensation and costs?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The liability of a Party to indemnify the other is reduced according to how far events at the other Party's risk contributed  to the risk event (see Clause 83.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Nov 9, 2012 by Rob Glasspool