How is the liability of a Party to indemnify the other affected if events at the other Party’s risk contributed to the claims, proceedings, compensation and costs?

+1 vote
342 views

How is the liability of a Party to indemnify the other affected if events at the other Party’s risk contributed to the claims, proceedings, compensation and costs?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer
It is reduced according to how far the event's at the other Party's risk contributed to the claims et al (see Clause 83.2).
answered Oct 10, 2012 by BuiltIntelligence (870 points)  