How should the Contractor deal with loss of and damage to the works, Plant and Materials?

How should the Contractor deal with loss of and damage to the works, Plant and Materials?

1 Like

He promptly replaces loss of and repairs damage to the works, Plant and Materials unless instructed otherwise by the Project Manager, until the Defects Certificate has been issued (see Clause 82.1).