Does the Contractor carry the risk of any events before the start date?

+1 vote
353 views

 Does the Contractor carry the risk of any events before the start date?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

No. Only events between the start date and issue of the Defects Certificate which are not carried by the Employer are Contractor’s risks (see Clause 81.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)