At whose risk is loss of or wear or damage to the parts of the works taken over by the Employer, before issue of the defects certificate, due to an event occurring before take over which was not itself an Employer’s risk?

+1 vote
326 views

At whose risk is loss of or wear or damage to the parts of the works taken over by the Employer, before issue of the defects certificate, due to an event occurring before take over which was not itself an Employer’s risk?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The event is at the Contractor’s risk (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)