Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,366 questions

5,756 answers

1,276 comments

Register its Free

Download here

At whose risk is loss of or wear to the parts of the works taken over by the Employer after issue of the Defects Certificate?

+1 vote
319 views

At whose risk is loss of or wear to the parts of the works taken over by the Employer after issue of the Defects Certificate?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer
The event is at the Employer’s risk (see Clause 80.1).
answered Oct 10, 2012 by BuiltIntelligence (870 points)