At whose risk is loss of or wear to the parts of the works taken over by the Employer after issue of the Defects Certificate?

+1 vote
330 views

At whose risk is loss of or wear to the parts of the works taken over by the Employer after issue of the Defects Certificate?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer
The event is at the Employer’s risk (see Clause 80.1).
answered Oct 10, 2012 by BuiltIntelligence (870 points)