Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,872 questions

6,320 answers

1,507 comments

Register its Free

Download here

At whose risk is loss or wear or damage to the works and any Plant and Materials retained on site by the Employer after a termination?

+1 vote
332 views

At whose risk is loss or wear or damage to the works and any Plant and Materials retained on site by the Employer after a termination?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The event is at the Employer’s risk except loss, wear or damage due to the activities of the Contractor on the Site after the termination (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)