At whose risk is loss or damage to the works, Plant and Materials due to strikes, riots and civil commotion not confined to the Contractor’s employees?

+1 vote
342 views

At whose risk is loss or damage to the works, Plant and Materials due to strikes, riots and civil commotion not confined to the Contractor’s employees?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The event is at the Employer’s risk (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)