Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,591 questions

6,002 answers

1,372 comments

Register its Free

Download here

At whose risk is loss or damage to the works, Plant and Materials due to war, civil war, rebellion, revolution, insurrection, military or usurped power?

+1 vote
339 views

At whose risk is loss or damage to the works, Plant and Materials due to war, civil war, rebellion, revolution, insurrection, military or usurped power?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The event is at the Employer’s risk (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)