Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,868 questions

6,316 answers

1,502 comments

Register its Free

Download here

At whose risk is loss of or damage to Plant and Materials supplied to the Contractor by the Employer, or Others on the Employer’s behalf?

+1 vote
343 views

 At whose risk is loss of or damage to Plant and Materials supplied to the Contractor by the Employer, or Others on the Employer’s behalf?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

If the Employer has not received and accepted the Plant and Materials, the event is at the Employer’s risk. If the Contractor has received and accepted the Plant and Materials, the event is at the Contractor’s risk (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)