Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

What are compensation events?

+4 votes
447 views
asked Sep 14, 2012 in Compensation Events by anonymous  
retagged Sep 15, 2012 by Admin

1 Answer

+2 votes
 
Best answer
They are events which affect Prices, the Completion Date or a Key Date and do not arise from the Contractor’s fault. Under other contract they would typically called claims, changes, variations, etc. These events entitle the Contractor to be compensated. A list of compensation events is in core Clause 60.1.

Other contracts would typically called them claims, changes, variations, etc.
answered Sep 15, 2012 by Admin (290 points)  
edited May 3, 2014 by Chris Corr