What are compensation events?

+4 votes
435 views
asked Sep 14, 2012 in Compensation Events by anonymous   11 68 95
retagged Sep 15, 2012 by Admin

1 Answer

+2 votes
 
Best answer
They are events which affect Prices, the Completion Date or a Key Date and do not arise from the Contractor’s fault. Under other contract they would typically called claims, changes, variations, etc. These events entitle the Contractor to be compensated. A list of compensation events is in core Clause 60.1.

Other contracts would typically called them claims, changes, variations, etc.