At whose risk are Claims, proceedings, compensation and costs payable which are due to negligence, breach of statutory duty or interference with any legal right by the Employer or by any person employed or contracted to him except the Contractor?

+1 vote
328 views

At whose risk are Claims, proceedings, compensation and costs payable which are due to negligence, breach of statutory duty or interference with any legal right by the Employer or by any person employed or contracted to him except the Contractor?

asked Oct 10, 2012 in Risk and Insurance by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The event is at the Employer’s risk (see Clause 80.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)