How are the Contractor’s costs which are not included in the Defined Cost treated?

+1 vote
393 views

How are the Contractor’s costs which are not included in the Defined Cost treated?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

They are included in the Fee as stated in Clause 52.1.

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool