Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

What does Defined Cost include?

+1 vote
395 views

What does Defined Cost include?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

It includes: amounts calculated using percentages and rates outlined in the Contract Data; amounts at competitively tendered prices; and any rebates and taxes which can be recovered (see Clause 52.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool