Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,590 questions

6,001 answers

1,372 comments

Register its Free

Download here

Is interest for a late payment compounded?

+1 vote
374 views

 Is interest for a late payment compounded?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Yes, for payments which are over a year late, interest is compounded. For payments less than one year late, the interest applied is the annual base rate (see Clause 51.4).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool