How long does it take for a certified payment to be made?

+1 vote
339 views

How long does it take for a certified payment to be made?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Within three weeks of the assessment date or within the period stated in the Contract Data if one is stated (see Clause 51.2).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool