What if a change reduces the amount due?

+1 vote
355 views

 What if a change reduces the amount due?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

Then a payment is made by the Contractor to the Employer (see Clause 51.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)