How long does the Project Manager have to certify a payment?

+1 vote
361 views

How long does the Project Manager have to certify a payment?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

One week. Within a week of each assessment date, the Project Manager certifies payment (see Clause 51.1).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool