What happens if the Employer does not include within his payment to the Contractor the correct amount of sales tax or VAT?

+1 vote
338 views

What happens if the Employer does not include within his payment to the Contractor the correct amount of sales tax or VAT?

asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Contractor should inform the Employer and the Project Manager that his payment does not include the correct amount of VAT/sales tax. The missing amount of sales tax/VAT is then a debt of the Employer.

answered Oct 10, 2012 by BuiltIntelligence (870 points)  