Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

Where is tax which the Employer is required to pay the Contractor included?

+1 vote
357 views
Where is tax which the Employer is required to pay the Contractor included?
asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

 In the amount due; Clause 50.2 states that this is where such taxes are to be included.

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool
Its also worth flagging up on your activity schedule whether VAT is included or excluded.