Where is tax which the Employer is required to pay the Contractor included?

+1 vote
349 views
Where is tax which the Employer is required to pay the Contractor included?
asked Oct 10, 2012 in Payment by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

 In the amount due; Clause 50.2 states that this is where such taxes are to be included.

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 24, 2012 by Rob Glasspool
Its also worth flagging up on your activity schedule whether VAT is included or excluded.