When does the Project Manager assess the amount of payment due?

When does the Project Manager assess the amount of payment due?

1 Like

At each assessment date. The Project Manager decides when the first assessment date occurs; it should suit the procedures of the Parties and not be later than the assessment interval after the starting date. Successive assessment dates are: at Completion; and at the end of each assessment interval until four weeks after the Supervisor has issued the Defects Certificate (see Clause 50.1).