An event which is not one of the other compensation events stated in the contract has stopped the Contractor from completing the works. Is this a compensation event?

+1 vote
338 views

An event which is not one of the other compensation events stated in the contract has stopped the Contractor from completing the works. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The relevant compensation event is clause 60.1 (19).  "Stops" is a strong test and means that it is not just difficult or more expensive to complete the works. The event also has to be one which:

  • neither Party could prevent,
  • an experienced Contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for it and
  • is not one of the compensation events stated in the contract.
answered Oct 10, 2012 by BuiltIntelligence (870 points)  