Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,500 questions

5,901 answers

1,325 comments

Register its Free

Download here

There has been a breach of contract by the Employer. Is this a compensation event?

+1 vote
583 views

There has been a breach of contract by the Employer. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

A breach of contract by the Employer which is not one of the other compensation events in the contract (listed in Clause 60.1) is a compensation event (see Clause 60.1(18)).

This clause was added into the 2nd edition of the contract to capture events whereby the Contractor would haver to sue under contract law for the breach as opposed to go throught the compensation event mechanisms of the contract. This is cheaper and quicker etc.

There is also an argument for saying that this clause also applies when the Project Manager or Supervisor are acting as a agent's of the Employer.

 

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 18, 2012 by Jon Broome