Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,751 questions

6,168 answers

1,429 comments

Register its Free

Download here

The Project Manager made assumptions about the effects of a compensation event which later proved to be incorrect. Is this a compensation event?

+1 vote
388 views

The Project Manager made assumptions about the effects of a compensation event which later proved to be incorrect. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

+1 vote
 
Best answer

The Project Manager may state assumptions to be used in the assessment of a compensation event (see Clause 61.6). If these are found to be wrong, the Project Manager notifies a correction and this is a separate compensation event (see Clause 60.1(17)).

Only the work affected by the changed assumption are included in the assessment of this subsequent compensation event and it is not a reason or excuse to re-visti the whole of the initial compensation event.

answered Oct 10, 2012 by BuiltIntelligence (870 points)  
edited Oct 18, 2012 by Jon Broome