The Employer has not provided materials, facilities and samples for tests and inspections as stated in the works information. Is this a compensation event?

+1 vote
342 views

The Employer has not provided materials, facilities and samples for tests and inspections as stated in the Works Information. Is this a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 18, 2012 by Jon Broome

1 Answer

0 votes
 
Best answer

Yes. Clause 40.2 states that the Employer is required to provide materials, facilities and samples for tests as stated in the Works Information. Failure to do so results in a compensation event (see Clause 60.1(16)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)  