Is an event which is the Employer’s risk a compensation event?

+1 vote
446 views

Is an event which is the Employer’s risk a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

An event which is an Employer’s risk stated in the contract (Employer’s risks are in Clause 80.1) is a compensation event (see Clause 60.1(13)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)