Do the weather measurements have to be recorded on Site?

0 votes
358 views

Do the weather measurements have to be recorded on Site?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The data routinely recorded at a weather station close to the Site could be used as an alternative to recording on the Site. If there is not a weather station nearby, the weather measurements should be made using gauges and equipment installed at the place stated in the Contract Data.

answered Oct 10, 2012 by BuiltIntelligence (870 points)