Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,496 questions

5,900 answers

1,321 comments

Register its Free

Download here

Do the weather measurements have to be recorded on Site?

0 votes
352 views

Do the weather measurements have to be recorded on Site?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

The data routinely recorded at a weather station close to the Site could be used as an alternative to recording on the Site. If there is not a weather station nearby, the weather measurements should be made using gauges and equipment installed at the place stated in the Contract Data.

answered Oct 10, 2012 by BuiltIntelligence (870 points)