Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,591 questions

6,001 answers

1,372 comments

Register its Free

Download here

How is adverse weather assessed as a compensation event?

0 votes
403 views

How is adverse weather assessed as a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Only the difference between the weather measurement and the weather which the weather data show to occur on average less frequently than once in ten years is taken into account in assessing a compensation event (Clause 60.1(13)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)