Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,761 questions

6,181 answers

1,431 comments

Register its Free

Download here

What if no weather data can be obtained?

0 votes
339 views

 What if no weather data can be obtained?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Where no recorded data is available, the assumed weather data is entered in the Contract Data.

answered Oct 10, 2012 by BuiltIntelligence (870 points)