What if no weather data can be obtained?

0 votes
340 views

 What if no weather data can be obtained?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Where no recorded data is available, the assumed weather data is entered in the Contract Data.

answered Oct 10, 2012 by BuiltIntelligence (870 points)