How is adverse weather which meets the tests in Clause 60.1(13) assessed?

0 votes
373 views

 How is adverse weather which meets the tests in Clause 60.1(13) assessed?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Only the difference between the weather measurement and the weather which the weather data show to occur on average less frequently than once in ten years is taken into account in assessing a compensation event (see Clause 60.1(13)).

answered Oct 10, 2012 by BuiltIntelligence (870 points)