At whose risk is adverse weather that has occurred more frequently than once in ten years?

0 votes
377 views

 At whose risk is adverse weather that has occurred more frequently than once in ten years?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Adverse weather which does not meet the tests in Clause 60.1(13) is at the Contractor’s risk in relation to both cost and time.

answered Oct 10, 2012 by BuiltIntelligence (870 points)