Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,590 questions

6,001 answers

1,372 comments

Register its Free

Download here

What if there is an ambiguity or inconsistency within the Site Information when assessing a compensation event for physical conditions?

0 votes
413 views

What if there is an ambiguity or inconsistency within the Site Information when assessing a compensation event for physical conditions?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

If there is an ambiguity or inconsistency within the Site Information, the Contractor is assumed to have taken into account the physical conditions more favourable to doing the work (see Clause 60.3).

answered Oct 10, 2012 by BuiltIntelligence (870 points)