NEC ECC: Can you add to the Activity Schedule in NEC 3 Option C

0 votes
29 views
A Contractor has missed an Activity of their Activity Schedule, this was listed on the Works Information.  can this be added in?
asked Jun 27 in Main options by Lee Jennings (240 points)  

1 Answer

0 votes
Yes the Contractor can by all means propose a change to the activity schedule, but not to change the Prices i.e. they can add items to the activity schedule but would have to decrease other activity schedule items to be able to put cost against the new items.

Errors in the activity schedule for items that were in the Works Information under option A are Contractor risk.
answered Jun 27 by Glenn Hide Panel Member (87,260 points)