Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,319 questions

5,698 answers

1,262 comments

Register its Free

Download here

What are the implications if an event doesn't meet the physical conditions tests in Clause 60.1(12)?

+1 vote
359 views

What are the implications if an event doesn't meet the physical conditions test in Clause 60.1(12)?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  
edited Oct 19, 2012 by Chris Corr

1 Answer

0 votes
 
Best answer
The event is not a compensation event
answered Oct 19, 2012 by Chris Corr (9,410 points)