NEC ECC: Submitting quotations for rejected CE’s

0 votes
47 views
Should you submit a quotation for a CE even if the PM had rejected the notification ?
asked May 20 in Compensation Events by KP (140 points)  

1 Answer

0 votes
Not a lot of point in submitting a quote if they have rejected the principle that is a CE - as they fill simply "file" the quote either in the bin or the shredder. Furthermore if you are using a cloud based system to manage the flow of NEC communications, it won't let you submit a quote into the system if the PM has not agreed it is a CE and requested a quote from you.

You would be better spent with your time beefing up your argument as to why it is a CE in the first place, rather than simply submitting a quote for something the PM believes they will be paying nothing for what ever your quote says.
answered May 20 by Glenn Hide Panel Member (84,800 points)