In judging the physical conditions for assessing a compensation event, the Contractor is assumed to have taken into account what?

0 votes
367 views

In judging the physical conditions for assessing a compensation event, the Contractor is assumed to have taken into account what?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer
  • The Site Information,
  • Publicly available information referred to in the Site Information,
  • Information obtained from a visual inspection of the Site and,
  • Other information which an experienced contractor could reasonably be expected to have or to obtain (see Clause 60.2).
answered Oct 10, 2012 by BuiltIntelligence (870 points)