Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,591 questions

6,002 answers

1,372 comments

Register its Free

Download here

In judging the physical conditions for assessing a compensation event, the Contractor is assumed to have taken into account what?

0 votes
357 views

In judging the physical conditions for assessing a compensation event, the Contractor is assumed to have taken into account what?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer
  • The Site Information,
  • Publicly available information referred to in the Site Information,
  • Information obtained from a visual inspection of the Site and,
  • Other information which an experienced contractor could reasonably be expected to have or to obtain (see Clause 60.2).
answered Oct 10, 2012 by BuiltIntelligence (870 points)