What are the three tests for assessing whether unexpected physical conditions constitute a compensation event?

0 votes
364 views

What are the three tests for assessing whether unexpected physical conditions constitute a compensation event?

asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer
  • The physical conditions are within the Site,
  • The physical conditions are not weather conditions and
  • An experienced contractor would have judged at the Contract Date that the conditions have such a small chance of occurring that it would have been unreasonable for him to have allowed for them (see Clause 60.1(12)).

 

answered Oct 10, 2012 by BuiltIntelligence (870 points)