NEC ECC - Notify a CE under X2.1

0 votes
46 views
Under NEC3, does X2.1 in itself become the compensation event i.e. 'We notify a compensation event which is a change in the law under Option X2' or does an event under 60.1 have to be referenced. If the latter, which event?
asked Mar 26 in Main options by AGQS (180 points)  

1 Answer

0 votes
Your first answer is correct. This would be a compensation event under X2.1. Not all compensation events are in clause 60.1. There are a few in other secondary options or option B clauses as well.
answered Mar 26 by Glenn Hide Panel Member (82,630 points)