Expert advice in minutes not days. Register it's free and ask your first question now.
ReachBack is a free community help desk for construction professionals run by Built Intelligence. A library of high-quality questions from real users with answers delivered and curated by industry experts.

5,617 questions

6,029 answers

1,389 comments

Register its Free

Download here

NEC ECC: Costs on critical path

0 votes
48 views
We are a Contractor on an NEC3 option C contract. The Project Manager wants us to spread our prelim costs across multiple Compensation Events which run concurrent with a Compensation Event that forms the critical path. We have put all of our prelim costs on the critical path event. Is this the correct approach or can the Project Manager insist we do it his way?
asked Mar 19 in Compensation Events by Cowboygeorge (230 points)  

1 Answer

+1 vote
 
Best answer
Your approach is correct, preliminary costs are a function of time and you only recover additional preliminary costs when there is an extension of time i.e. the CE is on or affects the critical path.

Having said this, in an Option C ECC it makes absolutely no difference provided that in total amount of preliminary costs you recover for the CE that was on the critical path is the same. In Option C payment is based on Defined Cost plus Fee not the Activity Schedule. The only function of the Activity Schedule is to establish the initial target and the final target when all of the compensation events are added to it.

So what I'm saying is if you are entitled to £10k in preliminary costs for the CE on the critical path, does it matter if you recover the £10k on that CE or across four CEs at £2.5k each? From a commercial perspective the result is the same.
answered Mar 19 by Neil Earnshaw Panel Member (28,820 points)  
selected Mar 19 by Neil Earnshaw