If the CE requires the provision of equipment that meets the criteria of item 27, but it is owned by the Contractor; is the correct course of action to establish a market rate for the equipment by evidencing alternative supplier quotes/ historical ‘re-hire’ invoices then applying the fee to that?
Or, given its your own plant and thereby deemed to included an element of overhead & profit - should fee then not be applied? My opinion is do what the contract says - establish a market rate and add fee, however if you own the plant isn’t this fee on fee?