How can disputes about delays caused by the Supervisor’s inspections be avoided?

0 votes
323 views
How can disputes about delays caused by the Supervisor’s inspections be avoided?
asked Oct 10, 2012 in Compensation Events by BuiltIntelligence (870 points)  

1 Answer

0 votes
 
Best answer

Wherever possible, the Works Information should include estimates of the time that the Supervisor needs for any of his tests. This will avoid arguments about what constitutes unnecessary delays.

answered Oct 10, 2012 by BuiltIntelligence (870 points)