How can disputes about delays caused by the Supervisor’s inspections be avoided?

How can disputes about delays caused by the Supervisor’s inspections be avoided?

Wherever possible, the Works Information should include estimates of the time that the Supervisor needs for any of his tests. This will avoid arguments about what constitutes unnecessary delays.