NEC ECC: Fail to reply quotation by Project Manager

0 votes
43 views
The Project Manager fails to reply a quotation  within the time allowed. Can Contractor notifies the Project Manager the quotation is deemed to be accepted?
asked 6 days ago in Compensation Events by mkd890 (320 points)  

1 Answer

0 votes
The Contractor first has to notify (in writing) the lack of response, and after a further two weeks of silence only then would it be deemed accepted.
answered 6 days ago by Glenn Hide Panel Member (80,560 points)